Electric Mining Truck Service: Who Does What, and Costs

Electric mining truck service is shared between the truck maker, its dealer, the battery supplier and trained mine staff. Large-truck plans are still taking shape on trial sites, so compare scope before price.

Authored by Farmonaut Research & Content Team
Reviewed and verified by Farmonaut Mining & Mineral Exploration Team
Updated 5 November 2026 ยท 15 min read
Sentinel-2 Satellite View Of Kansanshi Copper-Gold Mine, North-Western Province, Zambia
Sentinel-2 true-colour composite of Kansanshi copper-gold mine, North-Western Province, Zambia (12.09ยฐS, 26.42ยฐE). Contains modified Copernicus Sentinel data, 2022 to 2026, processed in Google Earth Engine.

Key takeaways

  • Caterpillar had seven Early Learner battery haul trucks in testing worldwide in June 2026 (Rio Tinto release).
  • Service models in use include dealer support, service level agreements, batteries as a service, in-house power systems and trolley contractors.
  • SRK’s 2024 desktop study models about US$3 million saved per 150-tonne truck over 10 years; results depend on diesel and power prices.
  • US MSHA rules require equipment to be de-energized, and locked out or otherwise secured, before mechanical work.
  • Boliden’s Aitik trolley pilot doubled speed from 15 to 30 km/h on its 700-metre line (Boliden).
In this article
  1. What an electric mining truck is, in three types
  2. Who provides electric mining truck service
  3. What an electric truck service contract should cover
  4. What changes in the workshop
  5. Electric vs diesel haul truck costs
  6. Field results from electric haul trucks
  7. Where large electric haul trucks stand
  8. How electrifying mining trucks reduces emissions
  9. Underground: where electric trucks fit first
  10. Electric truck options for mining in South Africa and the region
  11. Autonomous electric trucks
  12. Limits of electric mining trucks
  13. How to plan electric truck service at your mine
  14. Frequently asked questions

Electric mining truck service is a mix of work split between the truck maker, its local dealer, the battery or power-system supplier and the mine’s own electricians. The fleet is still small: in June 2026 Caterpillar had seven Early Learner battery-electric haul trucks in testing worldwide. So most large-truck service plans are being written now, on trial sites. This guide shows who does what, what the contracts cover, what changes in the workshop and how to test the numbers for your own haul road.

It is written for mine maintenance staff, fleet planners and the managers who sign the contract. Underground battery trucks are further along than the ultra-class surface trucks, and we point out where that difference matters.

What an electric mining truck is, in three types

An electric mining truck is a haul vehicle whose wheels are driven by electric motors. That simple definition covers three machines with very different service needs, so it is worth separating them before comparing any quote.

Type Where the power comes from What service adds
Electric-drive (diesel-electric) A diesel engine runs a generator that feeds wheel motors Engine work stays; motor and inverter work is already routine at many large mines
Trolley-assist Overhead lines on the climb, through a roof-mounted pantograph; diesel or battery elsewhere Line, substation and pantograph upkeep, plus truck conversion
Battery-electric An onboard battery, charged at a station, swapped or charged under a line Battery monitoring, chargers, high-voltage isolation and battery replacement

This matters for searches about the electric drive mining truck market: many trucks sold as “electric drive” still burn diesel. Hitachi’s EH4000AC-3, for example, is an established diesel-electric platform, and the battery version is a prototype built on that same model. Ask any supplier which of the three it is pricing.

Who provides electric mining truck service

No single company model has won yet. The projects with published detail show five roles, and most sites use several at once.

The truck maker and its dealer

This is the familiar route. The Pilbara trial of two Cat 793 XE trucks is a joint effort, and Caterpillar dealer WesTrac was among those at the site demonstration. Early testing there passed 100 operating hours and 200 test laps, with the partners using the data to check assumptions about safety, technology and maintenance. Those are small numbers compared with the life of a truck, which is why long-term service prices for these models are hard to find in public.

Best for: mines that already run the brand and want one point of contact. Watch for: whether the dealer has trained high-voltage technicians and parts in your region, not only at head office.

Service level agreements from equipment suppliers

Underground suppliers already sell this in a more settled form. Sandvik’s southern African load-and-haul manager has said its service level agreements can include close monitoring and maintenance of the equipment, with first-time users getting extended technical support. The same article says the company’s own staff in the region are building those skills first, and customer staff follow.

Best for: first-time users and underground mines. Watch for: how quickly the skills pass to your own crew, and what the agreement costs once the first term ends.

Batteries as a service

Here the mine pays for the use of the battery and the supplier carries more of the battery risk. In the agreement between Vale and Epiroc for two Canadian sites, Epiroc monitors the batteries for predictive maintenance, guarantees their life and removes old packs, which then go to second uses and recycling. The deal came with 10 vehicles, three charging cabinets and seven charging posts.

Best for: mines that do not want to forecast battery life themselves. Watch for: the exact definition of end of life, who pays for damage, and what happens if the mine’s duty cycle is harder than planned.

Power-system developers

Some miners keep the battery work in the family. Fortescue’s unit Fortescue Zero develops and integrates the power systems while Liebherr and XCMG build the trucks. That gives the miner direct control but also leaves it responsible for fixing what it designed.

Best for: very large fleets with engineering depth. Watch for: split responsibility when a fault could sit in either the truck or the power system.

Electrical contractors and the mine’s own team

Trolley lines bring in a different trade. At Aitik in Sweden, Boliden worked with ABB and Eitech on the electrical infrastructure, and Caterpillar and Pon Equipment on the truck conversion. At Kansanshi in Zambia, Hitachi describes First Quantum as having in-house trolley technology and working with 2,600 V systems.

Best for: long, steady uphill hauls at sites with reliable power. Watch for: line moves as the pit changes, since a trolley section that no longer sits on the main ramp stops paying for itself.

What an electric truck service contract should cover

Public contract prices are rare, so compare offers on scope first. These are the lines we would want in writing before signing. They are a planning checklist based on the projects in this guide, not a standard form.

  • Battery health: who reads the data, how often, and who owns it after the contract ends.
  • Battery end of life: the capacity level that triggers replacement, and who removes, moves and recycles the old pack.
  • Availability: a target with a clear definition. Does charging time count as available or not?
  • Chargers and lines: whether the truck contract includes them, or whether a separate contractor answers for them.
  • Parts: stock held on site or in-country, and delivery times for inverters, motors and battery modules.
  • Software: who may change battery and charging settings, and whether updates can be refused during peak production.
  • Training: how many of your people reach which level of high-voltage authorisation, and by when.
  • Fire and damage response: the plan for a damaged pack, including access for the site’s emergency team.
  • Exit: what happens to tools, data and spare parts if you change supplier.

What changes in the workshop

The work moves from engines to electrical systems. SRK Consulting, in a 2024 desktop study of 150-tonne trucks, attributes lower maintenance to simpler mechanical design and the absence of complex exhaust systems. Tyres, brakes, suspension, frames, dump bodies and hydraulics stay on the job list. A heavy battery can also add weight to carry, so the tyre and road plan still needs attention.

  • Gone or reduced: oil and filter changes on the engine, fuel system work, exhaust treatment.
  • New or larger: battery and cooling checks, high-voltage cable inspection, insulation testing, charger upkeep, pantograph wear on trolley trucks.
  • Unchanged: tyres, structural inspection, hydraulics, haul road care.

Regenerative braking, which turns braking energy back into stored charge, may reduce load on the mechanical brake parts on a downhill loaded or empty leg, but the real saving depends on the route. Check it with data from your own road before writing it into a budget.

High-voltage safety and lockout

This is the biggest change for fitters. In US metal and non-metal mines, MSHA rules say electrically powered equipment must be de-energized before mechanical work, with power switches locked out, or other measures taken to stop the equipment being energized, and warning notices posted and signed by the people doing the work. The underground rule has the same wording. A battery adds a practical problem to this: it stores energy even when the truck is off the charger, so isolation has to follow the maker’s procedure. Other countries have their own rules, so confirm the requirement with your mine regulator.

Skills to build

Sandvik’s southern African manager calls the expertise to maintain and service these machines a key part of the infrastructure, alongside the chargers. In practice that points to three groups: all site staff need awareness training for what not to touch, fitters need to work safely around isolated systems, and a smaller group of qualified electrical staff handle fault-finding on live or stored-energy systems.

Electric vs diesel haul truck costs

The best public cost comparison we found is the SRK study above. It is a consultancy’s desktop analysis, not field results, so treat it as a method rather than a promise. For a 150-tonne truck with a one-hour cycle, it compares 100 litres of diesel an hour at US$1 per litre with about 275 kWh costing around US$35, a 65% cut in energy cost per hour. It reports savings of about US$3 million over 10 years, after several battery replacements, with the extra purchase price recovered by the third year.

Chart

Energy cost to run a 150-tonne truck for one hour

US$ per hour, SRK modelled case

US$0US$30US$60US$90US$120US$100DieselUS$35ElectricSource: SRK Consulting, Ghosh, Gain and De, 2024.
US$0US$30US$60US$90US$120US$100DieselUS$35ElectricSource: SRK Consulting, Ghosh, Gain and De, 2024.
The gap rests on assumed prices: US$1 per litre of diesel and about 275 kWh an hour for US$35.

Three cautions go with those figures. The savings are driven by the diesel and power prices assumed, so a mine with expensive power or cheap diesel gets a different answer. The study covers 150-tonne trucks, well below the 240-tonne class planned for the Pilbara. And field cost data for large trucks is still thin, because the commercial models have not yet built up a long service history. BHP’s and Rio Tinto’s trial exists partly to test technical readiness, infrastructure needs and commercial feasibility; after it, each company will decide its next phase separately.

The older figures you may see online, such as exact hourly costs and yearly maintenance bills for every electric truck, generally have no named source. Use the calculator below with your own quotes instead.

Calculator

How fast would an electric truck pay back on your haul?

Enter your own fuel, power, service and purchase figures in US$.

L/hour

US$/L

kWh/hour

US$/kWh

hours

US$

US$

US$
3.9 yearssimple payback on the extra cost
  • Energy saving per hour (US$): $64
  • Total saving per year (US$): $385,500

Example values only, not a benchmark or a quote. Fuel and power use follow SRK’s 2024 150-tonne example; diesel and power prices are examples, use today’s price. Service costs and the extra purchase price are placeholders: use your written quotes. All money is US$. Excludes chargers unless you add them to the extra purchase price.

Field results from electric haul trucks

Results vary by mine and truck size, and most come from the operators or suppliers involved, as reported by SRK. Note that the two biggest gains below come from smaller underground machines, not ultra-class surface trucks.

Chart

Reported gains from electric trucks at named mines

% change against diesel; each bar is a different measure at one site

0%15%30%45%60%New Afton: mucking cycle timecut56%Brucejack: more tonnes hauled42%Brucejack: higher speed22%Boliden: cycle time cut15%Source: SRK Consulting 2024, reporting Boliden, New Afton and Brucejack results.
0%15%30%45%60%New Afton: mucking cycle time cut56%Brucejack: more tonnes hauled42%Brucejack: higher speed22%Boliden: cycle time cut15%Source: SRK Consulting 2024, reporting Boliden, New Afton andBrucejack results.
Compare with care: these measures differ, and the largest gains are from smaller underground machines.

Boliden’s own pilot gives the clearest trolley numbers. On the 700-metre line at Aitik, speed doubled from 15 to 30 km/h, saving 70 seconds a trip, and Boliden put the diesel saving at 830 cubic metres a year at the site. It expected a saving of 5,500 cubic metres a year once the Aitik and Kevitsa expansions were complete. ICMM also records the Aitik line as a test of the system in temperatures reaching -40 C.

At the Brucejack gold mine in Canada, then run by Pretivm, SRK reports a Sandvik Z50 truck at more than 90% machine availability, with battery swaps under 10 minutes. These figures are a useful yardstick to request from a supplier: ask for availability and swap time from a named site, on the same definition you will use in your contract.

Where large electric haul trucks stand

This table sums up the programmes we could confirm, with the date of each report. It covers selected public projects, not every electric truck in service.

Site or company Truck Charging Reported status
Fortescue, Pilbara Liebherr T 264, 240 t, plus XCMG 6 MW static charger, about 30 minutes First power system fitted; first truck expected to run before the end of 2026 (May 2026)
BHP and Rio Tinto, Jimblebar Two Cat 793 XE Early Learner Static, with in-motion charging next Trial under way; next steps decided separately after it (status June 2026; plan per 2025 release)
First Quantum, Kansanshi Hitachi EH4000AC-3 battery prototype Overhead lines while moving Over 4,000 km and 30,000 t in the June 2024 to August 2025 trial; commercial deployment targeted for financial 2027 (April 2026)
Boliden, Aitik and Kevitsa Converted trucks on trolley lines Overhead lines on climbs Staged rollout planned to 2022 (Boliden report)
Vale, two Canadian sites 10 Epiroc battery vehicles Charging cabinets and posts Batteries-as-a-service deal as announced by the companies (July 2020)

Fortescue’s plans are the largest found here. Its 2024 deal covered 475 machines, including 360 autonomous battery-electric trucks, worth US$2.8 billion. In September 2025 it said XCMG would supply up to half of the 300 to 400 trucks it now expects to need, with Liebherr amended to at least the other half. By May 2026, its first production power system had been fitted to a T 264 with a 2.6 MWh battery, and its executives said it would rely on bigger batteries and fast chargers instead of a pantograph.

At Kansanshi the approach is the reverse: a smaller battery that charges under the line. Hitachi argues this allows continuous operation without stopping to charge, and reported zero CO2 from truck operations in the trial, a result that reflects Zambia’s largely hydro power. These two designs lead to very different service jobs: one has a charger fleet to maintain, the other has overhead lines.

How electrifying mining trucks reduces emissions

A diesel truck emits at the tailpipe. An electric truck moves those emissions to wherever its power is made, so the grid decides most of the benefit. SRK puts haul trucks at about 174 Mt of CO2 equivalent a year, or 40-50% of emissions from mining machinery, citing IDTechEx. Sandvik’s Deon Lambert makes the limit plain: battery machines cannot improve on an older cable-trailing fleet’s footprint if the power still comes from a coal-fired grid. Fortescue’s answer is to build its own renewable grid, which it expects to complete by 2028 at a reported cost of more than $6 billion, currency not stated in the report (May 2026).

Chart

Daily power cost vs diesel truck cost at one mine

US$ per day, low and high of the reported range, Huolinhe coal mine, China

LowHighUS$0US$500US$1,000US$1,500US$2,000Electric truck powerUS$263US$298Diesel truckUS$1,480US$1,970Source: SRK Consulting 2024, reporting a Xiangtan Electric conversion.
LowHighUS$0US$500US$1,000US$1,500US$2,000Electric truck powerUS$263US$298Diesel truckUS$1,480US$1,970Source: SRK Consulting 2024, reporting a Xiangtan Electricconversion.
One conversion at one mine, included as a field example of the energy cost gap.

Partial electrification still counts. Boliden estimated that the trolley system at Aitik would cut transport emissions over the mine’s life by 15%, and the Kevitsa system would cut emissions over its mine life by 9%. For wider context on site impacts, see our guides to environmental issues in mining and ways to reduce the impact of mining. For the wider site, a sibling page covers battery electric mining equipment.

The seven environmental impacts of mining, explained in clay (2:31)

โ–ถ The seven environmental impacts of mining, explained in clay (2:31) ยท 2:31

Underground: where electric trucks fit first

Underground mines have an extra reason to switch: diesel fumes and heat must be cleared with ventilation. Suppliers already offer a wide range; Sandvik describes battery machines from 4-tonne loaders in 2 to 3 metre tunnels to 65-tonne trucks in 5 to 6 metre tunnels. Its LH518B loader can swap its own battery in six minutes without a crane or forklift, which cuts one kind of service equipment from the plan. See our review of the underground mining equipment market for makers and sizing.

Electric shuttle cars are a related search. These are low-profile haulers used in room-and-pillar coal mines, and many already run on a trailing power cable. Their service needs centre on the cable and motor, and they are a different category from the rigid haul trucks in this guide.

Electric truck options for mining in South Africa and the region

South Africa has a long history with this idea: Boliden notes that trials of electric mine trucks took place there in the 1980s. Today, the main public regional reference for large surface trucks is Kansanshi in nearby Zambia. For a South African mine, the questions to ask early are about grid reliability and carbon intensity, since Sandvik’s Lambert suggests combining on-mine renewables with battery machines where grid power is unreliable. Ask suppliers for local technicians and in-country parts, by name and number, rather than a general promise of regional support.

Autonomous electric trucks

Why do so many projects pair electric and driverless trucks? Fortescue’s order, for example, specified autonomous trucks. Charging adds planned stops to a shift, and a computer-run dispatch system can schedule these without a driver change. That is the reasoning; the field record at large scale is still short. Mining-industry readers can also see our short video on what AI systems do at a mine. For service teams, the point is that autonomy adds sensors and software to the maintenance list on top of the battery work.

What an AI mining app does across finding, planning and running a mine (3:52)

โ–ถ What an AI mining app does across finding, planning and running a mine (3:52) ยท 3:52

Limits of electric mining trucks

  • Payload: the Hitachi prototype was running a test payload of about 200 tonnes, with plans to match its diesel counterpart in later versions.
  • Charging time: SRK cites 1 to 1.5 hours for a full recharge, while Fortescue targets about 30 minutes with a 6 MW unit. Each truck parked at a charger still needs covering in the production plan.
  • Power supply: several 6 MW chargers running together can be a serious demand on a remote site’s power system.
  • Standards: SRK notes there is no unified standard for battery design and chemistry, which can tie a mine to one supplier’s parts and tools.
  • Timelines: dates move. Fortescue’s programme has been revised along the way, as the 2025 supplier change shows, so build slack into any fleet plan.

How to plan electric truck service at your mine

  1. Map the haul. Record grade, length and loaded direction for each route. Long loaded climbs favour trolley lines.
  2. Measure the power. Check grid capacity, reliability and carbon intensity, and how they compare with your diesel cost.
  3. Pick the type. Decide between trolley-assist, static charging or both before you ask for prices.
  4. Request like-for-like quotes. Use the contract list above, and ask for data from a named reference site.
  5. Run a small trial. Track availability, energy per tonne, tyre wear and service hours against your diesel trucks on the same road.
  6. Train before delivery. Get isolation procedures and emergency plans approved before the first truck arrives.

Infographic

Service planning in 5 steps

  1. 1Map the haulGrade, length and loaded direction.
  2. 2Measure powerCapacity, reliability and carbon.
  3. 3Pick the typeTrolley, static charging or both.
  4. 4Compare quotesSame scope, named reference sites.
  5. 5Trial and trainTrack data; approve isolation plans.

Plans also depend on how the pit will change. Satellite imagery and survey data can show how pits, dumps and haul roads have moved over time, which helps when deciding where a fixed charger or line should go. Haul costs feed into wider mining margins and all-in costs, so test any change at that level too.

Farmonaut’s mining work covers satellite mapping of mine sites and is not a truck service provider. Other Farmonaut pages cover fleet management, carbon footprinting, traceability, product traceability, an admin app, a satellite and weather API, loan and insurance verification and sustainable forestry.

A quick look at Farmonaut Mining Pro and its satellite mapping (4:56)

โ–ถ A quick look at Farmonaut Mining Pro and its satellite mapping (4:56) ยท 4:56

Frequently asked questions

Who services electric mining trucks?

Usually a combination of the truck maker and dealer, the battery or power-system supplier, electrical contractors for lines and chargers, and trained mine staff. The split is set by the contract.

How much does electric mining truck service cost?

We found no reliable public price list. Contracts are negotiated by site and scope. SRK’s 2024 study expects lower maintenance than diesel but gives it as part of a modelled total, so get written quotes and test them in the calculator.

Do electric mining trucks need less maintenance?

Engine and exhaust work falls away, according to SRK, but batteries, chargers and high-voltage systems are added. Tyres, frames and hydraulics remain. Long-term data on the largest trucks is still limited.

What is batteries as a service in mining?

The supplier monitors and guarantees the batteries, then replaces and removes them, as in the Vale and Epiroc agreement. It moves battery life risk away from the mine in exchange for a contract payment.

How long does it take to charge an electric haul truck?

SRK cites 1 to 1.5 hours for a full charge. Fortescue says its 6 MW charger will fully charge a truck in about 30 minutes. Trolley designs such as Hitachi’s charge while driving under the line.

How big is the battery on an electric haul truck?

It varies by design. SRK’s 150-tonne case uses 2,200 kWh for about 8 hours of work. Fortescue’s T 264 uses 2.6 MWh, as reported in May 2026. Trucks with overhead charging can carry smaller packs.

What is trolley assist on a mine truck?

The truck raises a pantograph and draws power from overhead lines on a set stretch, usually a loaded climb. At Aitik this doubled speed on the 700-metre line from 15 to 30 km/h.

How much CO2 does an electric mining truck save?

It depends on the power source. One conversion at the Huolinhe coal mine in China was estimated by SRK’s sources at 1,500 tonnes of CO2 a year, a figure for that truck. Hitachi reported zero truck-operation CO2 at Kansanshi on Zambia’s largely hydro grid.

Are electric mining trucks in commercial use?

Smaller underground battery trucks are on sale from suppliers such as Sandvik and Epiroc. Large surface battery trucks were still in trial or early rollout in the reports we reviewed from 2026. Hitachi has targeted its commercial deployment for financial 2027.

Is an electric-drive truck the same as a battery truck?

No. An electric-drive truck has wheel motors but gets its power from an onboard diesel generator. A battery truck stores its energy in a pack. Its service plan is different for that reason.

This page is for information only. It is not investment, legal or engineering advice. Confirm safety rules with your mine regulator and the truck maker.

Authored by: Farmonaut Research & Content Team

Reviewed and verified by: Farmonaut Mining & Mineral Exploration Team

Reviewed November 2026 against Rio Tinto, Boliden, Hitachi and ICMM publications, the SRK Consulting 2024 study and US MSHA rules at 30 CFR 56.12016 and 57.12016.

Farmonaut mining

Map your mining site from space

See how your pit, dumps and haul roads sit on the ground before you plan chargers or trolley lines.

Farmonaut Mining Pro 3D Target View (Sample, Synthetic Data)

Mining Pro sample view, synthetic data

Sources

  1. Rio Tinto, BHP, Rio Tinto and Caterpillar launch battery-electric haul truck trial in the Pilbara (2026): riotinto.com
  2. SRK Consulting, Decarbonizing Mining: Diesel vs Electric Haul Trucks (2024), summary: srk.com
  3. SRK Consulting, Ghosh, Gain and De, full paper (2024): cdn-web-content.srk.com
  4. Boliden, Climate-smart transport at Aitik and Kevitsa: boliden.com
  5. ICMM, Mining with principles at Boliden’s Aitik mine (2021): icmm.com
  6. Hitachi Construction Machinery, Feasibility trial of full battery dump truck (2024): hitachicm.com
  7. Mining Technology, Hitachi and FQM advance BEV haulage at Kansanshi (2026): mining-technology.com
  8. Mining Technology, Trialling the world’s first full battery trolley dump truck: mining-technology.com
  9. MINING.COM, Vale and Epiroc sign Batteries as a Service deal: mining.com
  10. MINING.COM, Fortescue US$2.8 billion Liebherr deal (2024): mining.com
  11. The Driven, Fortescue adds XCMG as electric truck supplier (2025): thedriven.io
  12. The Driven, Fortescue fits first 240-tonne truck and 6 MW charger (2026): thedriven.io
  13. Sub-Sahara Mining and Industrial Journal, Sandvik on battery vehicles in mining: subsaharamining.com
  14. 30 CFR 56.12016, Work on electrically-powered equipment (surface): ecfr.gov
  15. 30 CFR 57.12016, Work on electrically-powered equipment (underground): law.cornell.edu
  16. after it, each company will decide its next phase separately: riotinto.com



Discussion

Questions, corrections or field experience? Share them below. First-time comments are reviewed before they appear, and your email is never published.

No comments yet. Be the first to add a question or your experience.